Shades
Mid November 2006
Began to prepare for the construction of the shade structure to cover the two
greens at the front of the club. Existing shade structures were removed and the
area surrounding the greens prepared for the pouring of the footings.

January 2007
The footings were poured and the first part of the steel framework was erected

March
2007
Framework completed

April
2007
Membrane placed on framework
.jpg)
September 2007
 |